Project Timeline

Task 1: Abatement (approx. 3-4 weeks)

Abatement – Completed October 2017

Task 2: Demolition (approx. 35 days)

Commencing: October 18, 2017

Task 3: Excavation and Foundations (8-10 weeks)

Commencing: End of December, 2017

Task 4: Construction 

February 2018 – Spring 2019

Task 5: Marketing and Lease-up

Spring 2019